Sep. 24, 2009 |
1 |
The old press box is removed as work begins. |
Oct. 07, 2009 |
20 |
Preliminary land grading and surface compaction is completed. |
Oct. 09, 2009 |
1 |
Geological drillers arrive to test the soil for compaction. |
Oct. 13, 2009 |
12 |
Grading and surface compaction is completed. |
Oct. 21, 2009 |
2 |
Rain and inclement weather causes project delays. |
Dec. 01, 2009 |
25 |
Workers begin to diagram the layout of the stadium foundation. |
Dec. 07, 2009 |
25 |
Work continues laying out the framework of the stadium's foundation. |
Dec. 11, 2009 |
6 |
Final adjustments are made to the site layout before concrete foundation pillars are laid. |
Dec. 17, 2009 |
21 |
The concrete foundation anchor piers are laid out. |
Dec. 29, 2009 |
5 |
The foundation level of the new stadium complex nears completion. |
Jan. 08, 2010 |
5 |
Sections of the stadium's steel bleachers arrive and begin assembly. |
Jan. 12, 2010 |
17 |
Workers complete assembly of the steel bleacher framework. |
Jan. 23, 2010 |
39 |
Installation of various bleacher components in progress. |
Jan. 28, 2010 |
68 |
Finishing touches are added as project nears completion. |
Feb. 01, 2010 |
38 |
The nearly completed stadium after a dusting of snow. |
All Galleries |
285 |
View all galleries displayed on one page. |
Last Update: Monday, February 1st, 2010 - 38 new photos added to 02.01.10 Gallery and All Galleries.
|